Fervo Energy began selling electricity from its Cape Station enhanced geothermal plant to the grid on September 30, a day ahead of schedule. The first 100-megawatt phase's initial block took 23 months to build, with Fervo targeting 18 months for future blocks. Google and Southern California Edison have committed to buying power.