New Fluke research reveals 79% of UK data center operators blame electrical issues for disruptions, with only 17% confident in future AI readiness. A third report power limits GPU deployment, while 51% struggle to hire technicians, causing 38% of upgrade delays. Average grid connection wait times have risen to 14 months, threatening the national 6GW AI capacity target by 2030.